Sign In | Join Free | My himfr.com
Home > Clay Brick Production Line >

Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia

    Buy cheap Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia from wholesalers
     
    Buy cheap Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia from wholesalers
    • Buy cheap Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia from wholesalers
    • Buy cheap Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia from wholesalers
    • Buy cheap Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia from wholesalers
    • Buy cheap Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia from wholesalers

    Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia

    Ask Lasest Price
    Brand Name : Brictec
    Payment Terms : L/C, T/T,
    Certification : CE/SGS/ISO9001
    • Product Details
    • Company Profile

    Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia

    Dryer Machine in Brick Making Process and Products in Drying Chamber in MalaysiaDryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia

    1.Drying Chamber Section

    1:The cyclone base and main shaft motor on the top of the drying chamber have been installed,22 cyclone cone barrels have been installed and debugged,and 65 fans have been installed;

    2:The hot air pipe was produced on November 25,and the welding and assembly were completed;

    3:The concrete pouring of 2 out of 4 lines of the internal track of the drying chamber has been completed,and the other 2 lines are expected to be completed before December 8;

    4:The ferry lane construction at the vehicle exit has been completed;

    5:The hot air feeding blowers have been moved to the installation location;

    6:65 cyclone column piers have been poured.


    2.Tunnel Kiln Section

    1:After the completion of the ceiling beams,85 beams have been installed,along with 1512 secondary beams;

    2:The concrete pouring for the tunnel kiln ring beam has been finished;

    3:The construction of 2 return lines in the pre-drying chamber has been completed;

    4:The foundation construction of the ferry lane at the exit has been completed,and the steel bars of the track beam have been tied,awaiting track installation;

    5:The concrete pouring of the moisture exhaust chamber at the entry has been completed, and the case-in-place concrete top plate at the exit has also been completed;

    6:The ground of the return line has been excavated,and the crusher will be brought in next week to crush the ground,after which construction will commence;

    7:3780 lightweight high-aluminum hanging bricks and 3780 MG-26 polylight mullite ceiling bricks have been bonded.


    Quality Dryer Machine in Brick Making Process and Products in Drying Chamber in Malaysia for sale
    Inquiry Cart 0
    Send your message to this supplier
     
    *From:
    *To: Xi'an Brictec Engineering Co., Ltd.
    *Subject:
    *Message:
    Characters Remaining: (0/3000)